The new civic centre on Rust Ave. Photo / Michael Cunningham
Whangarei District Council’s almost $60 million civic centre is to be completed next month.
Whangarei District Council (WDC) general manager of corporate Alan Adcock said the practical completion of the centre on Rust Ave is scheduled for late February.
“[…] although some non-disruptive fit-out work is likely to extend slightly past that date,” he said.
“Despite numerous weather challenges over the last five months, we’re moving forward, with landscaping now progressing in the front of the building.”
Advertisement
The centre’s opening was originally planned for before October last year, but the building project had faced Covid-19 headwinds from its start, Adcock said.
Dates for milestone events, such as the official ribbon-cutting and the first meetings in the new council chambers, were yet to be confirmed but would likely take place in March.
Adcock said the forecast project completion cost for the project remained within the $59m budget approved at last June’s (WDC) council meeting.
WDC said in June 2018 the civic centre would cost $37m. Twelve months later, the centre was announced as costing $38m.
Advertisement
By February 2020, that had climbed by $10m to $48m, and the originally 5500sq m building increased in size to 7000 sq m, enlarged in order to accommodate more people, including Waka Kotahi NZ Transport Agency.
However, taxpayer-funded Waka Kotahi has now indicated its staff will instead continue to work from its Bank St site until its current lease there expires, Adcock said.
Then, by April 2021, the revised cost in the wake of new quantity surveyors coming on board was $55.1m, which dropped to $54.1m after contingency allowances were reduced.
In June 2022, WDC voted to add another $5m to the building’s cost. This nine per cent increase took the cost of the 470-person building to $59m. It was the sixth cost hike in five years.
Adcock said at the time of the last June 2022 civic centre price increase that a lift in costs was not unique.
“This [$59 million] is obviously well above the previous approved budget of $48m, but it should be noted that the construction process coincided with unprecedented events arising from the Covid pandemic,” he said.
The civic centre will be the new working space for about 350 WDC staff. It will also be the new working space for about 50 inter-council Northland Transportation Alliance staff from WDC, Northland Regional Council, Kaipara District Council and Far North District Council. Council meetings will be held in its new council chambers.
The civic centre will include a ground floor café.
Other major WDC Whangārei projects completed in recent years include the $32m Te Matau ā Pohe bridge (2013), the $30m Whau Valley Water Treatment Plant (2022) and the $8m Whangārei Central Library (2006).
Local Democracy Reporting is Public Interest Journalism funded through NZ On Air